Amadeo progression - Foundations
21/06/2008
20/06/2008
19/06/2008
18/06/2008
06/06/2008
03/06/2008
02/06/2008
01/06/2008
31/05/2008
30/05/2008
29/05/2008
Related articles
-
Making of Amadeo's first armed concrete slab
20 June 2008 -
Installation of the iron reinforcement on the right part of Amadeo (2nd layer)
19 June 2008 -
Installation of the iron reinforcement on the right part of Amadeo (1st layer)
09 June 2008 -
Installation of Index Testudo Spunbond waterproofing layer
02 June 2008 -
Making of Amadeo's drainage layer and footer
01 June 2008







Foundations